HP StorageWorks 300 HP StorageWorks 300 Gateway Virtual Library System Install
HP StorageWorks 300 - Virtual Library System EVA Gateway Manual
View all HP StorageWorks 300 manuals
Add to My Manuals
Save this manual to your list of manuals |
HP StorageWorks 300 manual content summary:
- HP StorageWorks 300 | HP StorageWorks 300 Gateway Virtual Library System Install - Page 1
HP StorageWorks 300 Gateway Virtual Library System Installation 1 Identifying product components Inspect the contents of the box. In addition to the contents of the shipping cartons and an existing EVA, you will need a #1 and a #2 Phillips screwdriver, 1 Ethernet cable to connect to the existing - HP StorageWorks 300 | HP StorageWorks 300 Gateway Virtual Library System Install - Page 2
Select a rack location that meets the space, airflow, temperature, power, and electrical grounding requirements described in the HP StorageWorks 300 Gateway Virtual Library System user guide. For adequate airflow within the rack, use appropriate high airflow inserts in rack cabinet doors and observe - HP StorageWorks 300 | HP StorageWorks 300 Gateway Virtual Library System Install - Page 3
5 Install node in the rack 1. Align the rails on the node with the rails in the rack. 2. Slide the node fully into the rack. The rails on the node will lock into the rails on the rack. 3. With the node fully seated in the rack, tighten the thumbscrews just until the node bezel is secured to the rack - HP StorageWorks 300 | HP StorageWorks 300 Gateway Virtual Library System Install - Page 4
FC cable (not provided) to host port 1 (item 2 in the figure). Connect the other end to an external FC switch/fabric that connects to your tape backup hosts. Otherwise, connect a loopback plug to host port 1. 4. Connect one end of an FC cable (not provided) to device port 3 (item 3 in the figure - HP StorageWorks 300 | HP StorageWorks 300 Gateway Virtual Library System Install - Page 5
port (cable is provided) to access the command-line user interface at initial configuration (item 5 in the in the figure above). Connect the other end to an external FC switch/fabric that connects to your tape backup hosts. Otherwise, connect a loopback plug to host port 1. 3. Connect one end of an - HP StorageWorks 300 | HP StorageWorks 300 Gateway Virtual Library System Install - Page 6
get more detailed information. • The HP StorageWorks 300 Virtual Library System user guide • The HP website, http://www.hp.com • Your nearest HP authorized reseller (locations and telephone numbers of these resellers are given on the HP website) • HP technical support telephone numbers: - In North
HP StorageWorks 300 Gateway
Virtual Library System
Installation
WARNING:
Each node weights 16.78 kg (37 lb).
At least two people are required to lift and rack
mount each node.
CAUTION:
Parts can be damaged by electrostatic
discharge.
Keep parts in their containers until
needed.
Ensure that you are properly grounded
when touching static sensitive components.
RACK REQUIREMENTS:
HP supports the HP System E
racks and the HP 10000 Series racks for use with the
virtual library system (VLS). Other racks might also be
suitable, but have not been tested with the VLS.
CAUTION:
Make sure that the rack and all
equipment mounted in the rack has a reliable
ground connection. Verify that the total current of
the rack components does not exceed the current
rating of the power distribution unit or outlet
receptacles.
WARNING:
To reduce the risk of personal injury
or damage to the equipment, before installing
equipment be sure that:
•The rack leveling jacks are extended to the floor.
•The full weight of the rack rests on the leveling
jacks.
•The stabilizing feet are attached to the rack if it
is a single-rack installation.
•The racks are coupled together in multiple-rack
installations.
•Only one component is extended at a time.
A rack may become unstable if more than one
component is extended for any reason.
Inspect the contents of the box.
In addition to the
contents of the shipping cartons and an existing EVA,
you will need a #1 and a #2 Phillips screwdriver,
1 Ethernet cable to connect to the existing external
network, and 4 to 8 FC cables to connect from the
nodes to the external FC fabrics/switches.
1) Primary and
secondary VLS300
Gateway nodes
2) 100 Mb Ethernet
switch 2524
3) 1 Gb Ethernet switch
2824
4) 3 ft Ethernet cables (5)
5) USB LAN adapters (2)
6) 1U rack mounting
hardware kits and
documentation (3)
7) Power cords (6)
8) Documentation CD
and VLS Quick
Restore CDs
9) Loopback plugs
1
2
3
4
6
5
7
8
9
Identifying product components
1