HP Surestore L10 Rackmount Kit Installation Guide - Page 2

Mount the hub on the rails.

Page 2 highlights

Step 3: Verify hub operation. Before racking the FC-AL hub, make sure it is operationa1. 1. Plug one end of the PDU cable into the hub and the other into an appropriate power source (100 VAC or 240 VAC). 2. At the completion of the hub self test (15 sec.), the Power LED should be on and the Fault LED off. • If the hub passes the self test, unplug the cable and continue with the installation. • If the self test fails, see the troubleshooting section of the HP Fibre Channel Arbitrated Loop Hub Service and User Manual. Step 4: Mount the rails. 1. Slide a sheet metal nut on the outer back column at the selected rack location. Insert the tab of the left rail in the adjacent slot so that the holes on the rack, nut, and rail are aligned. 2. Align the mounting ear brackets on the hub with the rear holes in the assembled rails, and fasten with two 10-32 x .625 screws. Figure 4 Step 6: Install the plenum shroud. 1. Slide the plenum shroud onto the rails from the front of the rack. 2. Align the plenum shroud brackets with the front holes in the assembled rails and secure with the two remaining 10-32 x .625 screws. Figure 3 2. Attach the other end of the rail to the inner front column using another sheet metal nut and the same procedure. NOTE: Do NOT attach screws at this time. 3. Repeat items 1 and 2 to install the right rail. Step 5: Mount the hub on the rails. 1. Slide the hub into the rails with the FC ports facing the rear of the cabinet. Figure 5 Step 7: Plug in the hub. Attach the PDU cable to the receptacle on the hub and to the cabinet power source (PDU). Verify that the hub passes the self test. Replace filler panels over the plenum shroud to complete the installation. To attach FC-AL devices, refer to the Hewlett-Packard Fibre Channel Arbitrated Loop Service and User Manual (A3724-90006). KS+ Customer Order No. A3724-90005 Copyright • 1997 Printed in USA 8/97 A3724-96002  

  • 1
  • 2

Customer Order No.
A3724-90005
Copyright • 1997
Printed in USA 8/97
A3724-96002
±²³´µ¶·¸¹¹µ±
K
S
+
±
Step 3:
Verify hub operation.
Before racking the FC-AL hub, make sure it is
operationa1.
1.
Plug one end of the PDU cable into the hub
and the other into an appropriate power source
(100 VAC or 240 VAC).
2.
At the completion of the hub self test (15 sec.),
the Power LED should be on and the Fault
LED off.
If the hub passes the self test, unplug the
cable and continue with the installation.
If the self test fails, see the troubleshooting
section of the
HP
Fibre Channel Arbitrated
Loop Hub Service and User Manual
.
Step 4:
Mount the rails.
1.
Slide a sheet metal nut on the outer back
column at the selected rack location. Insert the
tab of the left rail in the adjacent slot so that the
holes on the rack, nut, and rail are aligned.
Figure 3
2.
Attach the other end of the rail to the inner
front column using another sheet metal nut and
the same procedure.
NOTE:
Do NOT attach screws at this time.
3.
Repeat items 1 and 2 to install the right rail.
Step 5:
Mount the hub on the rails.
1.
Slide the hub into the rails with the FC ports
facing the rear of the cabinet.
2.
Align the mounting ear brackets on the hub
with the rear holes in the assembled rails, and
fasten with two 10-32 x .625 screws.
Figure 4
Step 6:
Install the plenum shroud.
1.
Slide the plenum shroud onto the rails from the
front of the rack.
2.
Align the plenum shroud brackets with the
front holes in the assembled rails and secure
with the two remaining 10-32 x .625 screws.
Figure 5
Step 7:
Plug in the hub.
Attach the PDU cable to the receptacle on the hub
and to the cabinet power source (PDU). Verify
that the hub passes the self test.
Replace filler panels over the plenum shroud to
complete the installation.
To attach FC-AL devices, refer to the
Hewlett-Packard Fibre Channel
Arbitrated Loop Service and User Manual
(A3724-90006).