WARNING: To reduce the risk of personal injury from high-leakage current, verify earth connection before connecting the power supply. The summation of input power for multiple pieces of information technology equipment through the use of power products can result in high-leakage currents. If the total system leakage current for a system of components exceeds 3.5 mA: • The use of a detachable input power cord is prohibited. • The input power cord must be securely attached, and it should be connected to the AC mains by hardwiring or through the use of a non-residential, industrial-style plug that maintains positive earth connection. • If the total system leakage current through the ground conductor exceeds 5% of the input current per line under normal operating conditions, the system loads should be divided among multiple power connections. Required tools The following tools are required for installation: • Phillips screwdriver • Torx screwdriver Additional requirements If your facility or configuration requires an L5-20R plug, you must obtain a third-party L5-20R to NEMA 5-20P adapter before installing or connecting the H5M54A 1.9kVA 120V Basic PDU. Before you begin 5

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18

Before you begin 5
WARNING:
To reduce the risk of personal injury from high-leakage current, verify earth
connection before connecting the power supply.
The summation of input power for multiple pieces of information technology equipment through
the use of power products can result in high-leakage currents.
If the total system leakage current for a system of components exceeds 3.5 mA:
The use of a detachable input power cord is prohibited.
The input power cord must be securely attached, and it should be connected to the AC mains
by hardwiring or through the use of a non-residential, industrial-style plug that maintains
positive earth connection.
If the total system leakage current through the ground conductor exceeds 5% of the input
current per line under normal operating conditions, the system loads should be divided among
multiple power connections.
Required tools
The following tools are required for installation:
Phillips screwdriver
Torx screwdriver
Additional requirements
If your facility or configuration requires an L5-20R plug, you must obtain a third-party L5-20R to NEMA 5-20P
adapter before installing or connecting the H5M54A 1.9kVA 120V Basic PDU.