HP R12000/3 HP UPS R1500 G3 Installation Instructions - Page 3

Readying the equipment, Installing the mounting rails

Page 3 highlights

• Electrical requirements-All models require a dedicated (unshared) branch circuit, suitably rated for the specific UPS as stated in "Input specifications" in the user guide. Readying the equipment 1. Check the battery recharge date specified on the label that is affixed to the shipping carton. IMPORTANT: Do not use the battery if the recharge date has passed. If the date on the battery recharge date label has passed without the battery being recharged, contact an HP authorized service representative for directions. 2. Transport the packaged unit to its installation location. 3. Unpack the equipment near the rack where the unit will be assembled. CAUTION: Always plan the rack installation so that the heaviest item is on the bottom of the rack. Install the heaviest item first, and continue to populate the rack from the bottom to the top. Installing the mounting rails WARNING: To reduce the risk of personal injury or damage to the equipment, be sure that: • The leveling feet are extended to the floor. • The full weight of the rack rests on the leveling feet. • The stabilizing feet are attached to the rack if it is a single-rack installation. • The racks are coupled together in multiple-rack installations. • Only one component is extended at a time. A rack may become unstable if more than one component is extended for any reason. 1. Attach the side-mounting brackets to the unit. 2. Loosen the wing nuts or hex nuts, and then extend the brackets to the desired length. 3. Use the cage nut tool to install cage nuts or clip nuts into the rear of the rack. 4. Insert screws through the mounting rail into the cage nuts or clip nuts.

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8

Electrical requirements—All models require a dedicated
(unshared) branch circuit, suitably rated for the specific UPS as
stated in "Input specifications" in the user guide.
Readying the equipment
1.
Check the battery recharge date specified on the label that is
affixed to the shipping carton.
IMPORTANT:
Do not use the battery if the recharge date
has passed. If the date on the battery recharge date label
has passed without the battery being recharged, contact
an HP authorized service representative for directions.
2.
Transport the packaged unit to its installation location.
3.
Unpack the equipment near the rack where the unit will be
assembled.
CAUTION:
Always plan the rack installation so that the
heaviest item is on the bottom of the rack. Install the
heaviest item first, and continue to populate the rack from
the bottom to the top.
Installing the mounting rails
WARNING:
To reduce the risk of personal injury or
damage to the equipment, be sure that:
The leveling feet are extended to the floor.
The full weight of the rack rests on the leveling feet.
The stabilizing feet are attached to the rack if it is a
single-rack installation.
The racks are coupled together in multiple-rack
installations.
Only one component is extended at a time. A rack may
become unstable if more than one component is
extended for any reason.
1.
Attach the side-mounting brackets to the unit.
2.
Loosen the wing nuts or hex nuts, and then extend the brackets to
the desired length.
3.
Use the cage nut tool to install cage nuts or clip nuts into the rear
of the rack.
4.
Insert screws through the mounting rail into the cage nuts or clip
nuts.