Electrical installation Yes No Comments Is the electrician aware of all requirements and specifications highlighted in this document? (Required) Is the Power Distribution Unit (PDU) correctly installed? (Required) Is the tri-phase line-to line voltage inside the specified voltage range: 200- 220 V~ (±10%) or 380-415 V~ (-10%, +6%)? Specify nominal mains voltage: Is the single-phase line voltage inside the specified voltage range: 115-127 V~ (±10%) or 200-240 V~ (-10%, +6%)? Specify nominal mains voltage: Electrical configuration Yes No Do you need an Uninterrupted Power Supply (UPS)? If so, is it correctly installed? LX600 only: Will the power supply be more than five meters from the printer? If so, does the electrician understand that the power cables will require extensions? LX800 only: Will the power supply be more than five meters from the printer? If so, does the electrician understand that the single phase power cable will require an extension? LX800 only: A three-phase power cord is not supplied with the printer, does the electrician understand that a three-phase power cord must be provided according to printer specifications and local laws? If local regulations specify that you must use electrical plugs to connect the printer to the power supply, does the electrician have the required plugs ready for installation? Comments Networking requirements Yes No Have network connections been supplied? Do you have a LAN cable long enough to connect the printer to the network? Comments RIP requirements Yes No Is HP Scitex Onyx RIP (Production House) CQ756A installed on the computer? Is HP Scitex Caldera RIP (GrandRIP+) CQ755A installed on the computer? Do you have a color sensor that is compatible with the RIP? Comments Environmental requirements Yes No Have the temperature and humidity requirements been satisfactorily met in the print production area, and is there adequate ventilation or air conditioning? Comments 4 Chapter 2 Checklist ENWW

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7

Electrical installation
Yes
No
Comments
Is the electrician aware of all requirements and specifications highlighted in
this document?
(Required)
Is the Power Distribution Unit (PDU) correctly installed?
(Required)
Is the tri-phase line-to line voltage inside the specified voltage range: 200–
220 V~ (±10%) or 380–415 V~ (–10%, +6%)?
Specify nominal mains voltage:
Is the single-phase line voltage inside the specified voltage range: 115–127
V~ (±10%) or 200–240 V~ (–10%, +6%)?
Specify nominal mains voltage:
Electrical configuration
Yes
No
Comments
Do you need an Uninterrupted Power Supply (UPS)? If so, is it correctly
installed?
LX600 only: Will the power supply be more than five meters from the printer?
If so, does the electrician understand that the power cables will require
extensions?
LX800 only: Will the power supply be more than five meters from the printer?
If so, does the electrician understand that the single phase power cable will
require an extension?
LX800 only: A three-phase power cord is not supplied with the printer, does
the electrician understand that a three-phase power cord must be provided
according to printer specifications and local laws?
If local regulations specify that you must use electrical plugs to connect the
printer to the power supply, does the electrician have the required plugs
ready for installation?
Networking requirements
Yes
No
Comments
Have network connections been supplied?
Do you have a LAN cable long enough to connect the printer to the network?
RIP requirements
Yes
No
Comments
Is HP Scitex Onyx RIP (Production House) CQ756A installed on the
computer?
Is HP Scitex Caldera RIP (GrandRIP+) CQ755A installed on the computer?
Do you have a color sensor that is compatible with the RIP?
Environmental requirements
Yes
No
Comments
Have the temperature and humidity requirements been satisfactorily met in
the print production area, and is there adequate ventilation or air
conditioning?