HP ProLiant BL280c HP BladeSystem c-Class Site Planning Guide - Page 62
Sample installation schedule, Sample checklists
View all HP ProLiant BL280c manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 62 highlights
Sample installation schedule The following schedule lists the sequence of events for a typical system installation. For situations that prevent following this type of schedule, consider using a milestone schedule. • 60 days before installation o Floor plan design completed and sent to Hewlett-Packard (if required to be an HP task) • 30 days before installation o Primary power and air conditioning installation completed o Telephone and data cables installed o Fire protection equipment installed o Major facility changes completed o Special delivery requirements defined o Site inspection survey completed o Delivery survey completed o A signed copy of the site inspection and delivery survey sent to HP o Site inspection and predelivery coordination meeting arranged with an HP representative to review the inspection checklist and arrange an installation schedule • 7 days before installation o Final check made with an HP site preparation specialist to resolve any last minute problems Sample checklists Customer and Hewlett-Packard information checklist: Customer information Name: Street address: Phone: City or town: State or province: Zip or postal code: Primary customer contact: Secondary customer contact: Traffic coordinator: Hewlett-Packard information Sales representative: Survey representative: Order number: Sample site inspection checklist: No. Computer room Country: Phone: Phone: Phone: Phone: Date: Scheduled delivery date: Yes No Comment or date Preparing for installation 62