RA 3-Pole Selective Earth Resistance Measurement with Current Clamp, See

Page 23 highlights

Earth/Ground Tester Operation RA 3-Pole Selective Earth Resistance Measurement with Current Clamp The RA 3-pole Selective Earth Resistance Measurement with Current Clamp procedure is useful for the resistance measurement of different parallel sections of an earth/ground system. 1. Select 3 POLE . See Figure 6. 2. Connect test leads. Connect the supplied test lead (1.5 m) to terminal E/C1 and its other end to the ground system to be measured. Place two ground stakes in earth/dirt. Minimum distance between earth electrode (E/C1), probe (S/P2) and auxiliary earth (H/C2) should be at least 20 m. Connect stakes with 25 m and 50 m wires to H/C2 and S/P2 as shown. Connect current clamp with adapter cable as shown. 3. Push START.  indicates that measurement is in progress. For continuous measurement, continue to push the START button. 4.  indicates completed measurement. The result is kept on display until a new measurement is started or the rotary switch is turned. 15 MyFlukeStore Shop for Fluke products online at: www. .com 1.877.766.5412

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40

Earth/Ground Tester
Operation
15
R
A
3-Pole Selective Earth Resistance Measurement with Current Clamp
The R
A
3-pole Selective Earth Resistance Measurement with Current Clamp procedure is
useful for the resistance measurement of different parallel sections of an earth/ground
system.
1.
Select
3 POLE

. See Figure 6.
2.
Connect test leads.
Connect the supplied test lead (1.5 m) to terminal E/C1 and its other end to the
ground system to be measured. Place two ground stakes in earth/dirt. Minimum
distance between earth electrode (E/C1), probe (S/P2) and auxiliary earth (H/C2)
should be at least 20 m.
Connect stakes with 25 m and 50 m wires to H/C2 and S/P2 as shown.
Connect current clamp with adapter cable as shown.
3.
Push
START
.
indicates that measurement is in progress. For continuous
measurement, continue to push the START button.
4.
indicates completed measurement. The result is kept on display until a new
measurement is started or the rotary switch is turned.