HP rp5400 Site Preparation Guide - rp5400 - Page 27

Table 1-5, Site Inspection Checklist

Page 27 highlights

General Site Preparation Guidelines Site Inspection Table 1-5 Site Inspection Checklist Please check either Yes or No. If No, include comment# or date Comment or Date Computer room No. Area or condition Yes No 1. Is there a completed floor plan? 2. Is there adequate space for maintenance needs? Front 36 in (91.4 cm) minimum, Rear 36 in (91.4 cm) minimum are recommended clearances. 3. Is access to the site or computer room restricted? 4. Is the computer room structurally complete? Expected date of completion? 5. Is a raised floor installed and in good condition? 6. Is the raised floor adequate for equipment loading? 7. Are there channels or cutouts for cable routing? 8. Is there a remote console telephone line available with an RJ11 jack? 9. Is a telephone line available? 10. Are customer supplied peripheral cables and LAN cables available and of the proper type? 11. Are floor tiles in good condition and properly braced? 12. Is floor tile underside shiny or painted? If painted, judge the need for particulate test. Power and lighting No. Area or condition Yes No 13. Are lighting levels adequate for maintenance? 14. Are there AC outlets available for servicing needs? (i.e. vacuuming) 15. Does the input voltage correspond to equipment specifications? 15A Is dual source power used? If so, identify type(s) and evaluate grounding. Chapter 1 19

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33

Chapter 1
General Site Preparation Guidelines
Site Inspection
19
Table 1-5
Site Inspection Checklist
Please check either Yes or No. If No, include comment# or date
Comment
or Date
Computer room
No.
Area or condition
Yes
No
1.
Is there a completed floor plan?
2.
Is there adequate space for maintenance needs?
Front 36 in (91.4 cm) minimum, Rear 36 in
(91.4 cm) minimum are recommended
clearances.
3.
Is access to the site or computer room
restricted?
4.
Is the computer room structurally complete?
Expected date of completion?
5.
Is a raised floor installed and in good condition?
6.
Is the raised floor adequate for equipment
loading?
7.
Are there channels or cutouts for cable routing?
8.
Is there a remote console telephone line
available with an RJ11 jack?
9.
Is a telephone line available?
10.
Are customer supplied peripheral cables and
LAN cables available and of the proper type?
11.
Are floor tiles in good condition and properly
braced?
12.
Is floor tile underside shiny or painted? If
painted, judge the need for particulate test.
Power and lighting
No.
Area or condition
Yes
No
13.
Are lighting levels adequate for maintenance?
14.
Are there AC outlets available for servicing
needs? (i.e. vacuuming)
15.
Does the input voltage correspond to equipment
specifications?
15A
Is dual source power used? If so, identify type(s)
and evaluate grounding.