G130/G131 Product Support Guide Installation Requirements 1. Temperature Range: 10°C to 32°C (50°F to 89.6°F) 2. Humidity Range: 15% to 80% RH 3. Ambient Illumination: Less than 2,000 lux (do not expose to direct sunlight) 4. Ventilation: 3 times/hour/person or more 5. Do not expose the machine to the following: 1) Direct cool air from an air conditioner 2) Direct heat from a heater 6. Do not install the machine in areas that get exposed to corrosive gas. 7. Install the machine locations lower than 2,500 m (8,200 ft.) above sea level. 8. Install the machine on a strong, level base. 9. Do not install the machine in areas that get strong vibrations. Machine level Front to back: Within 5 mm (0.2") Right to left: Within 5 mm (0.2") Power Requirements • Input voltage level: 120 V, 60 Hz: More than 11A (G130) / 12A (G131) • Permissible voltage fluctuation: ±10 % • Do not place anything on the power cord • The required wall outlet is a NEMA 5-15R CAUTION: Make sure the outlet and the machine are grounded. CAUTION: Insert the plug firmly into the outlet. CAUTION: Avoid using an extension cord or adapter plug. Installation Times Mainframe: 30 minutes Peripherals: Peripherals, which can be installed by users: PFU/LCT 15 minutes Duplex Unit 15 minutes IEEE1284 5 minutes IEEE1394 5 minutes Blue tooth 5 minutes Wireless LAN 5 minutes USB Host I/F 5_____minutes Direct Camera Printing 5_____minutes Gigabit Ethernet 5_____minutes Peripherals, which should be installed by technicians: Finishers 15 minutes Punch Kit 15 minutes NOTE: These are installation times for after the machine has been removed from the carton. Version - 1.0

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24

G130/G131 Product Support Guide
Version – 1.0
Installation Requirements
1.
Temperature Range:
10
°
C to 32
°
C (50
°
F to 89.6
°
F)
2.
Humidity Range:
15% to 80% RH
3.
Ambient Illumination:
Less than 2,000 lux (do not expose to direct sunlight)
4.
Ventilation:
3 times/hour/person or more
5.
Do not expose the machine to the following:
1) Direct cool air from an air conditioner
2) Direct heat from a heater
6.
Do not install the machine in areas that get exposed to corrosive gas.
7.
Install the machine locations lower than 2,500 m (8,200 ft.) above sea level.
8.
Install the machine on a strong, level base.
9.
Do not install the machine in areas that get strong vibrations.
Front to back:
Within 5 mm (0.2")
Right to left:
Within 5 mm (0.2")
Power Requirements
Input voltage level: 120 V, 60 Hz: More than 11A (G130) / 12A (G131)
Permissible voltage fluctuation: ±10 %
Do not place anything on the power cord
The required wall outlet is a NEMA 5-15R
CAUTION:
Make sure the outlet and the machine are grounded.
CAUTION:
Insert the plug firmly into the outlet.
CAUTION:
Avoid using an extension cord or adapter plug.
Installation Times
Mainframe:
30
minutes
Peripherals:
Peripherals, which can be installed by users:
PFU/LCT
15
minutes
Duplex Unit
15
minutes
IEEE1284
5
minutes
IEEE1394
5
minutes
Blue tooth
5
minutes
Wireless LAN
5
minutes
USB Host I/F
____________________5_
____minutes
Direct Camera Printing
______________5_
____minutes
Gigabit Ethernet____________________5__
___minutes
Peripherals, which should be installed by technicians:
Finishers
15
minutes
Punch Kit
15
minutes
NOTE:
These are installation times for after the machine has been removed from the carton.
Machine level