General Site Preparation Guidelines Electrical Factors Most computer room installations are equipped with the following fire protection devices: • Smoke detectors • Fire and temperature alarms • Fire extinguishing system Additional safety devices are: • Circuit breakers • An emergency power cutoff switch • Devices specific to the geographic location for example, earthquake protection Lighting Requirements for Equipment Servicing Adequate lighting and utility outlets in a computer room reduce the possibility of accidents during equipment servicing. Safer servicing is also more efficient and, therefore, less costly. For example, adequate lighting reduces the chances of connector damage when cables are installed or removed. The minimum recommended illumination level is 70 foot-candles (756 lumens per square meter) when the light level is measured at 30 inches (76.2 cm) above the floor. Working Space for Server Access The recommended working space for performing maintenance on the server is three feet (91.4cm). The work space shall permit at least a 90° opening of equipment doors or hinged panels. When planning for the working space area, consider whether access to the server will be at the front, side, or rear of the server. Power Consumption When determining power requirements, you must consider any peripheral equipment that will be installed during initial installation or as a later update. Refer to the applicable documentation for such devices to determine the power required to support these devices. Electrical Load Requirements (Circuit Breaker Sizing) NOTE Local Authority Has Jurisdiction (LAHJ) and should make the final decision regarding adherence to country- specific electrical codes and guidelines. It is good practice to derate power distribution systems for one or more of the following reasons: • To avoid nuisance tripping from load shifts or power transients, circuit protection devices should never be run above 80% of their root-mean-square (RMS) current ratings. • Safety agencies derate most power connectors to 80% of their RMS current ratings. Power Quality The hp Integrity rx2620 Server is designed to operate over a wide range of voltages and frequencies. The server is tested and shown to comply with EMC Specification EN55024. However, damage can occur if these ranges are exceeded. Severe electrical disturbances can exceed the design specifications of the equipment. 18 Chapter 2

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43

General Site Preparation Guidelines
Electrical Factors
Chapter 2
18
Most computer room installations are equipped with the following fire protection devices:
Smoke detectors
Fire and temperature alarms
Fire extinguishing system
Additional safety devices are:
Circuit breakers
An emergency power cutoff switch
Devices specific to the geographic location for example, earthquake protection
Lighting Requirements for Equipment Servicing
Adequate lighting and utility outlets in a computer room reduce the possibility of accidents during equipment
servicing. Safer servicing is also more efficient and, therefore, less costly.
For example, adequate lighting reduces the chances of connector damage when cables are installed or
removed.
The minimum recommended illumination level is 70 foot-candles (756 lumens per square meter) when the
light level is measured at 30 inches (76.2 cm) above the floor.
Working Space for Server Access
The recommended working space for performing maintenance on the server is three feet (91.4cm). The work
space shall permit at least a 90
°
opening of equipment doors or hinged panels. When planning for the working
space area, consider whether access to the server will be at the front, side, or rear of the server.
Power Consumption
When determining power requirements, you must consider any peripheral equipment that will be installed
during initial installation or as a later update. Refer to the applicable documentation for such devices to
determine the power required to support these devices.
Electrical Load Requirements (Circuit Breaker Sizing)
NOTE
Local Authority Has Jurisdiction (LAHJ) and should make the final decision regarding
adherence to country- specific electrical codes and guidelines.
It is good practice to derate power distribution systems for one or more of the following reasons:
To avoid nuisance tripping from load shifts or power transients, circuit protection devices should never be
run above 80% of their root-mean-square (RMS) current ratings.
Safety agencies derate most power connectors to 80% of their RMS current ratings.
Power Quality
The hp Integrity rx2620 Server is designed to operate over a wide range of voltages and frequencies. The
server is tested and shown to comply with EMC Specification EN55024. However, damage can occur if these
ranges are exceeded. Severe electrical disturbances can exceed the design specifications of the equipment.