Site Preparation Guide HP Integrity rx7620 Server Fourth Edition Manufacturing Part Number : A7027-96032 October 2006 Printed in the U.S.A. © Copyright 1979-2006 HP Development Company, L.P. - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 2
release. September 2003. Second Edition Minor edits to general specifications. November 2003. Third Edition Minor edits. May 2004. Fourth Edition Consolidated the documentation for the rx7620-16 and the rx7620-DC into the rx7620. Updated system power requirements information in Appendix A. October - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 3
Internal Disk Devices for HP Integrity rx7620 Server 14 MP/SCSI Core I/O Board 14 Procurium LAN/SCSI Board 14 Mass Storage (Disk) Backplane 15 Server Description 16 Dimensions 16 System Chassis 16 A. System Specifications Dimensions and Weights 20 Electrical Specifications 21 Grounding 21 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 4
Contents Electrostatic Discharge Prevention 41 Acoustics 42 Facility Characteristics 43 Floor Loading 43 Windows 45 Space Requirements 46 Delivery Space Requirements 46 Operational Space Requirements 46 Equipment Footprint Templates 48 Computer Room Layout Plan 49 Power Plug Configuration - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 5
Contents v - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 6
Contents vi - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 7
Contents vii - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 8
Contents viii - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 9
HP Integrity rx7620 Server DIMMs 11 Table 1-4. DIMM Load Order 12 Table A-1. HP Integrity rx7620 Server Dimensions and Weights 20 Table A-2. HP Integrity rx7620 Server Component Weights 20 Table A-3. Power Cords 21 Table A-4. AC Power Specifications 22 Table A-5. Typical HP Integrity rx7620 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 10
Tables x - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 11
to Cell Board Block Diagram 5 Figure 1-5. HP Integrity rx7620 Server 8-Socket Block Diagram 7 Figure 1-6. Cell Board 8 Figure 1-7. Memory Subsystem 9 Figure 1-8. CPU Locations on B-15. L6-20 Power Cable 54 Figure B-16. Delivery Survey (Part 1 61 Figure B-17. Delivery Survey (Part 2 62 xi - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 12
Figures xii - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 13
Figures xiii - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 14
Figures xiv - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 15
to the HP 9000 rp7410 product in the IA-64 product line. The HP Integrity rx7620 Server shares the same hardware as the HP 9000 rp7410 with changes to the cell board, CPU modules, core I/O and the PCI-X backplane. The HP Integrity rx7620 Server provides increased performance over its predecessor - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 16
Introduction Overview Overview The HP Integrity rx7620 Server is a 10U, 8-socket Symmetric Multi-Processing, rack-mount server that accommodates up to 64 GB of memory, PCI-X I/O, and internal peripherals, including disks and DVD/tape. Its high availability features include N+1 hot-pluggable fans - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 17
Figure 1-2 HP Integrity rx7620 Server (without front bezel) Introduction Overview System Backplane The system backplane comprises the system clock generation logic, the on the system backplane. The "crossbar-less" back-to-back CC connection increases performance and reduces costs. Chapter 1 3 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 18
Introduction Overview Only half of the MP/SCSI reset and clock circuitry that propagates through the whole system. The central clocks drive all major chip set clocks. Therefore, these circuits represent a system wide single speed point to point data bus. The SBA can support up to 16 4 Chapter 1 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 19
Overview of these high-speed bi-directional rope links for a total aggregate bandwidth of approximately 4 GB/sec. Each LBA acts as a bus bridge, supporting either one or two ropes and capable of driving 33 Mhz or 66 Mhz for PCI cards. The LBAs can also drive for HP Integrity rx7620 Server systems. - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 20
Introduction Overview Table 1-1 PCI-X Slot Types I/O Partition Slot Devicea 0 8 PCI (33 or 66 MHz) / PCI-X (66 or 133 slot is used as a PCI slot then either the 33MHz or 66MHz PCI frequency is supported. If the slot is used as a PCI-X slot then either the 66MHz or 133MHz PCI-X frequency is - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 21
Introduction Detailed HP Integrity rx7620 Server Description Detailed HP Integrity rx7620 Server Description Figure 1-5 HP Integrity rx7620 Server 8-Socket Block Diagram PDH Cell Board 0 Memory Cell Board 0 Memory CPU CPU CC CPU CPU CPU CPU CC CPU CPU CC Link PDH DVD/ Tape Bulk - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 22
Interface. The buses include two Front Side Buses (FBS0 and FBS1), a Memory (MID) bus, a Crossbar (XB) bus, and an I/O bus. All these blocks come together at the CC chip. Figure 1-6 Cell Board The HP Integrity rx7620 Server has a 48V distributed power system and receives the 48V power from the - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 23
Introduction Detailed HP Integrity rx7620 Server Description Figure 1-7 shows a simplified view of the memory subsystem. It consists of two independent access paths, each path having its own address bus, control bus, data bus, and DIMMs. In practice, the CC - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 24
1 Socket 0 DIMMs The memory DIMMs used by the HP Integrity rx7620 Server are custom-designed by HP and are identical to those used in the Superdome server. Each DIMM contains SDRAM memory components and is qualified to run at 125MHz. The CPU chip set will not support traditional DRAMs. 10 Chapter - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 25
be loaded in sets of four at specific locations. For best performance, HP recommends loading sets of eight DIMMs. Table 1-3 HP Integrity rx7620 Server DIMMs DIMM Size 256 MB 512 MB 1 GB 2 GB 4 GB Total Capacity 8 GB 16 GB 32 GB 64 GB 128 GB Memory Component Density 64 megabit 128 megabit 256 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 26
Detailed HP Integrity rx7620 Server Description A quad seen in Figure 1-9 is a grouping of four DIMMs. Configurations with 8 or 16 Echelons 10 DIMMs = 5 Echelons 12 DIMMs = 6 Echelons 14 DIMMs = 7 Echelons 16 DIMMs = 8 Echelons Action Taken Install First Add Second Add Third Add Fourth Add Fifth - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 27
and sharing processes and memory space among the components. Each nPartition must have one root cell and may have both. The HP Integrity rx7620 Server has only two possible available on the Web at http://docs.hp.com Refer to HP System Partitions Guide: Administration for nPartitions for details. - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 28
HP Integrity rx7620 Server Description Internal Disk Devices for HP Integrity rx7620 Server In an HP Integrity rx7620 Server, the top internal disk drives connect to cell 1 through the core I/O for cell 1. Both of the bottom disk drives supported add-in PCI-X card. The Procurium board is hot - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 29
to disks are routed on the mass storage backplane, having connectors and termination circuitry. All disks are hot-pluggable. The HP Integrity rx7620 Server accommodates one internal removable media device. Therefore, only one power connector for a removable media device is required on the mass - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 30
The dimensions of the HP Integrity rx7620 Server are as follows: • server units per 2 m rack and upgrade of current 10U height products in the future are the main height constraints. System Chassis The mass storage section located in the front allows access to the 3.5-inch hard drives 16 Chapter 1 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 31
N+1 fully redundant BPSs. Figure 1-11 Right-Front View of HP Integrity rx7620 Server PCI-X cards Front panel display board PCI Power modules Cell removing the left side cover. The system backplane inserts by a guide/insertion mechanism using a single large jack screw assembly. SCSI ribbon- - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 32
Introduction Server Description Cell boards are accessed from the right side of the chassis behind a removable side cover. Figure 1-12 Left-Rear View of HP Integrity rx7620 Server System backplane MP/SCSI Core I/O Power Connectors 18 Chapter 1 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 33
A System Specifications This chapter describes the basic server configuration and its physical specifications and requirements. Appendix A 19 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 34
System Specifications Dimensions and Weights Dimensions and Weights This section provides dimensions and weights of the system components. Table A-1 HP Integrity rx7620 Server Dimensions and Weights Height Width Depth Weight - Pounds (kilograms) Standalone Packaged 17.3 in / 43.9 cm 35.75 in - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 35
System Specifications Electrical Specifications Electrical Specifications This section provides electrical specifications for HP Integrity rx7620 Servers. Grounding The site building shall provide a safety ground for each AC service entrance to all cabinets. Install a protective earthing conductor - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 36
the measured maximum worst case power consumption. This number represents the largest power consumption for the server under laboratory conditions, using aggressive software applications designed specifically to work the system at maximum loads and power consumption. DC-Powered Systems DC-powered - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 37
dissipation, noise emission, and airflow specifications for HP Integrity rx7620 Servers. Temperature and Humidity The cabinet is sea level up to 30° C at 10,000 feet. For optimum reliability and performance, the recommended operating range is 20° to 25° C Environmental Temperature Sensor To ensure - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 38
Cooling Table A-5 Typical HP Integrity rx7620 Server Configurations Cell Boards Memory Per Cell Board PCI Cards (assumes 10 watts each) DVDs Hard Disk Drives Core I/O Bulk Power Supplies Typical Power Typical Cooling Qty 2 2 2 1 GBytes Qty 16 16 8 8 4 8 4 8 Qty 2 0 0 0 Qty - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 39
System Specifications Environmental Specifications Airflow The HP Integrity rx7620 Server requires that the cabinet air intake temperature be between 68° and 77° F (20° and 25° C) at 960 CFM. Figure A-1 illustrates the location of the inlet - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 40
System Specifications System Requirements Summary System Requirements Summary This appendix summarizes the requirements that must be considered in preparing the site for the HP Integrity rx7620 Server. Power Consumption and Air Conditioning To determine the power consumed and the air conditioning - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 41
System Specifications System Requirements Summary Table A-7 Weight Summary (Continued) Component DVD Disk Drive Chassis with skins and front bezel cover Quantity Multiply By 2.2 lb / 1.0 kg 1.6 lb / 0.73 kg 131 lb / 59.42 kg Total weight Weight (kg) Appendix A 27 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 42
System Specifications System Requirements Summary 28 Appendix A - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 43
B General Site Preparation Guidelines Appendix B 29 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 44
in this guide are based specific electrical codes and guidelines. The LAHJ acronym will be used throughout this section. Proper design and installation of a power distribution system for the server practices, produces the most trouble-free operation. A detailed for equipment servicing) are important - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 45
Devices specific to the geographic location, such as earthquake protection Lighting Requirements for Equipment Servicing Adequate .2 cm) above the floor. Working Space for Server Access The recommended working space for performing maintenance on the server is three feet. The work space will permit - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 46
, testing cannot conclusively rule out loss of service. Therefore, adherence to the following guidelines provides the best possible performance of power distribution systems for server equipment: • A dedicated power source isolates the server power distribution system from other circuits in the - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 47
under the floor panels. Grounding Systems The server requires two methods of grounding: • Power distribution systems consist of several parts. HP recommends that these parts be solidly , building steel, or a conductive type cold water service pipe, provide an earth ground. Electrical Conduit Ground - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 48
be hazardous to personnel and might cause performance issues for the equipment. Dual power sources high-frequency ground return paths. Therefore, the server is shipped with a ground strap for and electrical service entrance ground at multiple connection points using a minimum #6 AWG (16 mm) - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 49
to service entrance ground and server equipment). The use of conductive floor tiles with this style of grid further enhances ground performance. The equipment 60SP010A 11/30/99 Equipment Grounding Implementation Details Connect all HP equipment cabinets to the site ground grid as follows: 1. Attach - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 50
HP equipment. Refer to the appropriate installation guide for installation procedures. Wiring Connections Expansion and contraction rates vary among different metals. Therefore, the integrity that can cause serious problems, such as erratic equipment that can destroy hard-to-replace components, - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 51
floor system for the most favorable room air distribution system (underfloor distribution). • Ensure a minimum ceiling height of 12 inches between the top of the server and the ceiling and that all ceiling clips are in place. • Allow 18 inches (or local code minimum clearance) from the top of the - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 52
included. For example, a person dissipates about 450 Btu per hour while performing a typical computer room task. At altitudes above 10,000 ft (3048 to air heat exchangers, which cool the air locally over the servers. A system called DataCoolTM is primarily used in high density environments of - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 53
General Site Preparation Guidelines Environmental Elements If a ceiling plenum return air system or a ducted ceiling return air system is used, the return air grilles in the ceiling should be located directly above the computer equipment cabinets. The following three types of air distribution - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 54
voltage potential. ESD can cause component damage during servicing operations. Paper feed problems on high-speed printers are usually encountered in low dust and microscopic particles in the site environment. Specifically, disk drives, tape drives, and some other mechanical devices can have bearing - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 55
contaminants are formed on the bottom of some raised floor tiles. Although this problem is relatively rare, it might be an issue within your computer room. cause permanent or intermittent failures on your electronic equipment, HP strongly recommends that your site be evaluated for metallic - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 56
General Site Preparation Guidelines Environmental Elements • Ensure that all equipment and flooring are properly grounded and are at the same ground potential. • Use conductive tables and chairs. • Use a grounded wrist strap (or other grounding method) when handling circuit boards. • Store spare - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 57
for the installation or operation of the server. Facility characteristics are: • Floor loading • Windows • Altitude effects Floor Loading The computer room floor must be able to support the total weight of the installed computer system as well as the weight of the individual cabinets as they are - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 58
floor panel can support (without failure) when a wheel of specified diameter and width is rolled across the panel. Computed by dividing total equipment weight by the for the installation of an HP Integrity rx7620 Server. Based on specific information provided by HP, Tate Access Floors has approved - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 59
Guidelines Facility Characteristics Table B-4 Typical Raised Floor Specifications (Continued) Itema Rating Concentrated loadb 1250 computers in a room with windows. Sunlight entering a computer room can cause problems. Magnetic tape storage media is damaged if exposed to direct sunlight. Also, - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 60
This section contains information about space requirements for an HP Integrity rx7620 Server. This data should be used as the basic be eliminated. The locations of lighting fixtures and utility outlets affect servicing operations. Plan equipment layout to take advantage of lighting and utility - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 61
Area 24.0 in 58.8 cm 36.0 in 88.2 cm 53.0 in. 129.9 cm Rack Rack 36 in. Service Area Rack Front 36 in. 36.0 in. 88.2 cm Server (Fully Extended) Space planning should also include the possible addition of equipment or other changes in space requirements. Equipment layout plans should - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 62
grid are drawn to the same scale (0.25 in. = 1 ft). These templates are provided to show basic equipment dimensions and space requirements for servicing. The service areas shown on the template drawings are lightly shaded. The equipment templates should be used with the floor plan grid to define the - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 63
General Site Preparation Guidelines Computer Room Layout Plan Computer Room Layout Plan Use the following procedure to create a computer room layout plan: 1. Remove the floor plan grid from the document. See Figure B-4. 2. Remove a copy of each applicable equipment footprint template. See Figure - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 64
General Site Preparation Guidelines Computer Room Layout Plan Figure B-4 Planning Grid Scale: 1/4 inch = 1 foot 60SP016A 12/20/99 50 Appendix B - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 65
based on the regional shipping destination. Female End of Power Cable The female end of the hp server is a C19 type plug that mates with the C20 receptacle in each power supply installed in the hp server. Figure B-5 C20 Male Receptacle (at power supply) Figure B-6 C19 Female Plug (on one end of - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 66
list is not meant to be all inclusive nor is this list meant to imply every plug shown is one that is available for the server. Figure B-7 Unterminated Plug Figure B-8 L6-20 Plug Figure B-9 IEC 309 Plug Figure B-10 CEE 7-7 Plug 52 Appendix B - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 67
Figure B-11 L6-30 Plug General Site Preparation Guidelines Power Plug Configuration Figure B-12 NEMA 5-20P Plug on left (receptacle on right) Figure B-13 ISI 32 Plug Appendix B 53 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 68
Power Plug Configuration Figure B-14 GB 1002 Plug Power Cable The power cable length and configuration will vary based on the region the server ships to. This is an example of one power cable configuration used to supply power to the server. Figure B-15 L6-20 Power Cable 54 Appendix B - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 69
conversion factors provided in this appendix are intended to ease data calculation for systems that do not conform specifically to the configurations listed in this Site Preparation Guide. Listed below are the conversion factors used in this document, as well as additional conversion factors which - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 70
schedule. • 7 days before installation - Final check made with an HP site preparation specialist to resolve any last minute problems NOTE Not all installations follow a schedule like the one noted above. Sometimes, a server is purchased through another vendor which can preclude a rigid schedule - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 71
Inspection Checklist Sample Site Inspection Checklist Table B-5 Customer and HP Information Customer Information Name: Phone No: Street Address: contact: Phone No.: Traffic coordinator: Phone No.: HP information Sales representative Order No: Representative making survey Date - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 72
AC outlets available for servicing needs? (i.e. vacuuming) 15. Does the input voltage correspond to equipment specifications? 15A Is dual source type(s) and evaluate grounding. 16 Does the input frequency correspond to equipment specifications? 17. Are lightning arrestors installed - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 73
purposes? 24. Is there a fire protection system in the computer room? 25. Is antistatic flooring installed? 26. Are there any equipment servicing hazards (loose ground wires, poor lighting, etc.)? Cooling No. Area or condition Yes No 27. Can cooling be maintained between 20 °C and - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 74
or recommendations should be entered on the special instructions or recommendations form. The following list gives examples of special instructions or issues: • Packaging restrictions at the facility, such as size and weight limitations • Special delivery procedures • Special equipment required for - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 75
General Site Preparation Guidelines Delivery Survey • Special security requirements applicable to the facility, such as security clearance Figure B-16 Delivery Survey (Part 1) DELIVERY CHECKLIST DOCK DELIVERY Is dock large enough for a semitrailer? Yes No Circle the location of the dock and - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 76
General Site Preparation Guidelines Delivery Survey Figure B-17 Delivery Survey (Part 2) ELEVATOR Fill in the following information if an elevator is required to move equipment. Capacity (lb or kg) Depth Height Width Depth Height Width STAIRS Please list number of flights and stairway - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 77
required to raise one pound of water one degree fahrenheit per hour, a common measure of heat transfer rate. C CompactPCI The newest specification for PCI-based industrial computers is called CompactPCI. It is electrically a superset of desktop PCI with a different physical form factor. See http - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 78
. The FCC (Federal Communications Commission) regulates a portion of this problem through Part 15 of their rules and regulations. Even more stringent . The PCI Industrial Computer Manufacturers Group (PICMG) controls the PICMG specification. Power factor The ratio of true power to apparent power in - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 79
General Site Preparation Guidelines Delivery Survey True power In an AC circuit, true power is the actual power consumed. It is distinguished from apparent power by eliminating the reactive power component that may be present. Typical input current The operating current of the product measured using - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 80
General Site Preparation Guidelines Delivery Survey 66 Appendix B - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 81
data communications cables, 36 dimensions and weights, 20 DIMM removing and replacing, 39 DIMMs, 9 memory, 9 disk, 40 internal, 15 storage backplane, 15, 20 MP core I/O, 4, 13, 14, 16, 17 MP/SCSI, 4, 14, 17 N noise emission specifications, 24 O operating environment, 23 P PCI backplane, 4, 14 PDH - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 82
space requirements, 46 equipment footprint templates, 48 system backplane, 4, 14, 17, 20, 23 system installation guidelines, 36 data communications cables, 36 wiring connections, 36 system specifications, 19 T typical installation schedule, 56 W wiring connections, 36 68 - HP Integrity rx7620 | Site Preparation Guide, Fourth Editon - HP Integrity rx762 - Page 83
Index 69
Site Preparation Guide
HP Integrity rx7620 Server
Fourth Edition
Manufacturing Part Number : A7027-96032
October 2006
Printed in the U.S.A.
© Copyright 1979-2006 HP Development Company, L.P.