TP-Link T1700X-16TS T1700X-16TSUN V1 Installation Guide - Page 21

Power On, 5 Initialization

Page 21 highlights

JetStream 10-Gigabit Smart Switch 4.4 Power On Plug in the negative connector of the provided power cord into the power socket of the device, and the positive connector into a power outlet as the following figure shown. 2 1 Figure 4-3 Connecting to Power Supply Note: The figure is to illustrate the application and principle. The power plug you get from the package and the socket in your situation will comply with the regulation in your country, so they may differ from the figure above. 4.5 Initialization After the device is powered on, it begins the Power-On Self-Test. A series of tests run automatically to ensure the device functions properly. During this time, its LED indicators will respond in the following order: 1. The PWR LED lights on all the time. The SYS LED and the LED indicators of all the ports keep off. 2. After over one minute, the LED indicators of all the ports will flash momentarily and then turn off. 3. A few seconds later, the SYS LED indicator will flash, which represents a successful initialization. Connection 16

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28

JetStream 10-Gigabit Smart Switch
Connection
16
4.4 Power On
Plug in the negative connector of the provided power cord into the power socket of the
device, and the positive connector into a power outlet as the following figure shown.
1
2
Figure 4-3
Connecting to Power Supply
Note:
The figure is to illustrate the application and principle. The power plug you get
from the package and the socket in your situation will comply with the regulation in
your country, so they may differ from the figure above.
4.5 Initialization
After the device is powered on, it begins the Power-On Self-Test. A series of tests run
automatically to ensure the device functions properly. During this time, its LED indica-
tors will respond in the following order:
1. The PWR LED lights on all the time. The SYS LED and the LED indicators of all the
ports keep off.
2. After over one minute, the LED indicators of all the ports will flash momentarily and
then turn off.
3. A few seconds later, the SYS LED indicator will flash, which represents a successful
initialization.