HP Scitex LX850 HP Scitex LX850 & LX820 Printers: Site Preparation Guide - - Page 10

System operation requirements, Electrical configuration

Page 10 highlights

Site preparation The Media Manager will not be covered. HP Scitex Caldera RIP ● Server Administration (Server, Configure, connection) ● GrandRip+ (Main, Tool, settings) ● Spooler ● Image Work Directory (Image Positioning and scale setting on the page, and so on) Profile creation will not be covered. System operation requirements Electrical configuration NOTE: An electrician is required for the setup and configuration of the building electrical system used to power the printer and also for printer installation. Make sure that your electrician is appropriately certified according to local regulations and supplied with all the information regarding the electrical configuration. Your printer requires the following electrical components to be supplied and installed by the customer, according to the Electrical Code requirements of the local jurisdiction of the country where the equipment is installed. 1. Printer electrical cabinet 2. Uninterruptible Power Supply (UPS) for single-phase line (recommended) 3. Power Distribution Unit (PDU) including single-phase branch circuit breaker 4. Power Distribution Unit (PDU) including three-phase branch circuit breaker 5. HP Internal Print Server computer NOTE: Remember that you are required to follow the local laws, regulations, and standards that pertain to the electrical installation of your printer. NOTE: The LX820 or LX850 are not supplied with a three-phase cable. 6 Chapter 2 Site preparation ENWW

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28

The Media Manager will not be covered.
HP Scitex Caldera RIP
Server Administration (Server, Configure, connection)
GrandRip+ (Main, Tool, settings)
Spooler
Image Work Directory (Image Positioning and scale setting on the page, and so on)
Profile creation will not be covered.
System operation requirements
Electrical configuration
NOTE:
An electrician is required for the setup and configuration of the building electrical system used
to power the printer and also for printer installation. Make sure that your electrician is appropriately
certified according to local regulations and supplied with all the information regarding the electrical
configuration.
Your printer requires the following electrical components to be supplied and installed by the customer,
according to the Electrical Code requirements of the local jurisdiction of the country where the
equipment is installed.
1.
Printer electrical cabinet
2.
Uninterruptible Power Supply (UPS) for single-phase line (recommended)
3.
Power Distribution Unit (PDU) including single-phase branch circuit breaker
4.
Power Distribution Unit (PDU) including three-phase branch circuit breaker
5.
HP Internal Print Server computer
NOTE:
Remember that you are required to follow the local laws, regulations, and standards that
pertain to the electrical installation of your printer.
NOTE:
The LX820 or LX850 are not supplied with a three-phase cable.
6
Chapter 2
Site preparation
ENWW
Site preparation