4. Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the top side panel and tighten. 5. Repeat steps 1 through 4 for the other top side panel. Installing the ground bonding rack option kit on HP 10000 G2 Series Rack fan kits From the grounding lug on the rack top to the grounding lug on the fan kit: 1. Place one end of a 15.24-cm (6-in) grounding strap over the grounding lug on the rack top. 2. Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the rack top and tighten. 3. Place the other end of the same grounding strap over the grounding lug on the perforated panel. 4. Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the perforated panel and tighten. From the grounding lug on the fan kit to the grounding lug on the egress slot: 1. Place one end of a 36.83-cm (14.5-in) grounding strap over the grounding lug on the fan kit. Installing the HP Ground Bonding Rack Option Kit 11

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19

Installing the HP Ground Bonding Rack
Option Kit 11
4.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the top
side panel and tighten.
5.
Repeat steps 1 through 4 for the other top side panel.
Installing the ground bonding rack option kit on HP 10000 G2 Series Rack fan kits
From the grounding lug on the rack top to the grounding lug on the fan kit:
1.
Place one end of a 15.24-cm (6-in) grounding strap over the grounding lug on the rack top.
2.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the rack
top and tighten.
3.
Place the other end of the same grounding strap over the grounding lug on the perforated panel.
4.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the
perforated panel and tighten.
From the grounding lug on the fan kit to the grounding lug on the egress slot:
1.
Place one end of a 36.83-cm (14.5-in) grounding strap over the grounding lug on the fan kit.