HP rp3440 Site Preparation Guide, Fifth Edition - HP 9000 rp3410/rp3440 - Page 26

Environmental Elements, Computer Room Preparation, Cooling Requirements

Page 26 highlights

General Site Preparation Guidelines Environmental Elements Environmental Elements The following environmental elements can affect a HP 9000 rp3410 or HP 9000 rp3440 server installation: • Computer room preparation • Cooling requirements • Humidity level • Air conditioning ducts • Dust and pollution control • Electrostatic discharge (ESD) prevention • Acoustics (noise reduction) Computer Room Preparation The following guidelines are recommended when preparing a computer room for a HP 9000 rp3410 or HP 9000 rp3440 server: • Locate the computer room away from the exterior walls of the building to avoid the heat gain from windows and exterior wall surfaces • When exterior windows are unavoidable, use windows that are double- or triple-glazed and shaded to prevent direct sunlight from entering the computer room • Maintain the computer room at a positive pressure relative to surrounding spaces • Use a vapor barrier installed around the entire computer room envelope to restrain moisture migration • Caulk and vapor seal all pipes and cables that penetrate the envelope • Use at least a 12-inch raised floor system for minimum favorable room air distribution system (underfloor distribution) • Ensure a minimum clearance of 12 inches between the top of the server cabinet and the ceiling to allow for return air flow and ensure that all ceiling tiles are in place • Allow 18 inches (or local code minimum clearance) from the top of the server cabinet to the fire sprinkler heads Cooling Requirements Air conditioning equipment requirements and recommendations are described in the following sections. Basic Air Conditioning Equipment Requirements The cooling capacity of the installed air conditioning equipment for the computer room should be sufficient to offset the computer equipment dissipation loads, as well as any space envelope heat gain. This equipment should include: • Air filtration • Cooling or dehumidification • Humidification 26 Chapter 2

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47

General Site Preparation Guidelines
Environmental Elements
Chapter 2
26
Environmental Elements
The following environmental elements can affect a HP 9000 rp3410 or HP 9000 rp3440 server installation:
Computer room preparation
Cooling requirements
Humidity level
Air conditioning ducts
Dust and pollution control
Electrostatic discharge (ESD) prevention
Acoustics (noise reduction)
Computer Room Preparation
The following guidelines are recommended when preparing a computer room for a HP 9000 rp3410 or HP
9000 rp3440 server:
Locate the computer room away from the exterior walls of the building to avoid the heat gain from
windows and exterior wall surfaces
When exterior windows are unavoidable, use windows that are double- or triple-glazed and shaded to
prevent direct sunlight from entering the computer room
Maintain the computer room at a positive pressure relative to surrounding spaces
Use a vapor barrier installed around the entire computer room envelope to restrain moisture migration
Caulk and vapor seal all pipes and cables that penetrate the envelope
Use at least a 12-inch raised floor system for minimum favorable room air distribution system (underfloor
distribution)
Ensure a minimum clearance of 12 inches between the top of the server cabinet and the ceiling to allow
for return air flow and ensure that all ceiling tiles are in place
Allow 18 inches (or local code minimum clearance) from the top of the server cabinet to the fire sprinkler
heads
Cooling Requirements
Air conditioning equipment requirements and recommendations are described in the following sections.
Basic Air Conditioning Equipment Requirements
The cooling capacity of the installed air conditioning equipment for the computer room should be sufficient to
offset the computer equipment dissipation loads, as well as any space envelope heat gain. This equipment
should include:
Air filtration
Cooling or dehumidification
Humidification