- HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 1
HP Linux Clusters QsNetII Cable Management Kit Installation Guide Part Number: AA-RVWCA-TE March 2004 Revision/Update Information: This is a new manual. This document describes how to install the QsNetII Cable Management Kit into an HP Model 10642 rack. Hewlett-Packard Company Palo Alto, California - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 2
contained herein is subject to change without notice. The only warranties for HP products and services are set forth in the express warranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP shall not be liable - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 3
the cables. • Facilitates servicing of the interconnect line cards and individual cables. 1 Audience HP service representatives and other persons You can download the documentation for components referenced in this installation guide from the following locations: • HP Model 10642 Rack: http:// - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 4
that you attach to the frame at the rear of the rack (not the rack columns) and provides a routing guide and support for cable bundles. This guide plate is required only for interconnects installed into the upper part of the rack. • Eighteen straps with hook-and-loop closures, which are supplied - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 5
screwdriver with a P2 bit is recommended. - One of the following: 3 8-inch long flat-blade screwdriver with a 0.25-inch wide blade. QsNetII Cable Management Kit Installation Guide 3 - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 6
the kit in any position other than those specified in Table 2. Doing so will put strain on the cable connections 4 QsNetII Cable Management Kit Installation Guide - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 7
1. If you are installing this cable management kit into an Interconnect Building Block (IBB) that contains two interconnects, you must first install the cable guide plates as described in step 1. If you are installing the kit into an IBB that contains one interconnect in the lower rack location only - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 8
) M6 x 16mm Screw (4X) Top Bracket Rear of Rack zk-2080 Figure 4 shows how to mount the rear bottom bracket. 6 QsNetII Cable Management Kit Installation Guide - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 9
Pin X1 Pin in Closed Y Position Pin in Open Position zk-2082 6. Orient a cable support bar so that the cable support hooks are on the right-hand side. Place the bottom of the bar between the flanges on as shown in shown in Figure 6, callout 2. QsNetII Cable Management Kit Installation Guide 7 - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 10
8 and 9 for the remaining seven cable support bars on both the front and back of the rack. 10 Cabling Procedure Follow the cabling sequence instructions for the interconnect cables as described in the documentation shown by callout 1 in Figure 7. 8 QsNetII Cab le Management Kit Installation Guide - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 11
a dual-interconnect IBB, you must route the cables down the guide plate and support them by using the cable straps as shown in Figure 2, callout do not interfere with the servicing of interconnect components. Figure 8 shows how to attach one of the straps to the cable guide plate. Figure 8: Bundling - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 12
instructions service operation is complete, swing the cable management bar up 90 degrees and release the spring-loaded retainer pin. Ensure that the pin is inserted firmly into the upper bracket. 7. Reconnect the cables to their respective ports. 10 QsNetII Cable Management Kit Installation Guide - HP Cluster Platform Hardware Kits v2010 | Linux Clusters QsNetII Cable Managemen - Page 13
described in the Service documentation for the model of interconnect. 1. Disconnect the cables and remove them from the hooks. Support any unfastened cables from the lower bracket. 5. You do not need to remove the cable guide plates. However, take care to route any disconnected cables out of the way
HP Linux Clusters
QsNet
II
Cable Management Kit Installation Guide
Part Number: AA-RVWCA-TE
March 2004
Revision/Update Information:
This is a new manual.
This document describes how to install the QsNet
II
Cable Management Kit into an HP Model
10642 rack.
Hewlett-Packard Company
Palo Alto, California