3 Site preparation checklist These questions must be answered before the printer is delivered. Table 3-1 Safety requirements Question Yes No Do those who will operate the printer have the technical training and experience necessary to be aware of hazards to which they may be exposed in performing a task, and to take appropriate measures to minimize the risks? (Required) Is there an emergency exit in the print production area, with easy access and free from any obstruction? Comments Table 3-2 Electrical installation requirements Question Yes No Comments Is the electrician aware of all requirements and specifications highlighted in this guide? (Required) Is the single-phase line voltage inside the specified voltage range, 200-240 V? (Required) Specify nominal mains voltage: Are there the dedicated lines to connect printer's power cords? NOTE: Do not use a power strip (relocatable power tap) to connect both power cords. (Required) Have branch circuit breakers (2 poles, 16 A/20 A general) been correctly installed for each dedicated line? (Required) Have the Residual Current Circuit Breaker (also known as Ground Fault Circuit Interrupter) (2 poles, 30 mA residual, at least 20A capacity) been correctly installed if required or recommended? (Required) Is the Power Distribution Unit (PDU) correctly installed? (Required) Are the grounding conductors properly installed for each wall receptacle (wall socket)? (Required) Are the wall receptacles (wall sockets) suitable for the power cord plug type provided by HP? (Required) Are the wall receptacles (wall sockets) and electrical installation suitable for the printer's rated current ? NOTE: See Wall receptacles and power cords on page 10 and Single-phase power on page 8 for further information. (Required) Are the wall receptacles (wall sockets) placed close enough to the printer that the plugs can be plugged and unplugged easily? (Required) Site preparation checklist 15

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21

Site preparation checklist
3
These questions must be answered before the printer is delivered.
Table 3-1
Safety requirements
Question
Yes
No
Comments
Do those who will operate the printer have the technical training and
experience necessary to be aware of hazards to which they may be exposed
in performing a task, and to take appropriate measures to minimize the
risks?
(Required)
Is there an emergency exit in the print production area, with easy access
and free from any obstruction?
Table 3-2
Electrical installation requirements
Question
Yes
No
Comments
Is the electrician aware of all requirements and specifications highlighted in
this guide?
(Required)
Is the single-phase line voltage inside the specified voltage range, 200–240
V?
(Required)
Specify nominal mains voltage:
Are there the dedicated lines to connect printer's power cords?
NOTE:
Do not use a power strip (relocatable power tap) to connect both
power cords.
(Required)
Have branch circuit breakers (2 poles, 16 A/20 A general) been correctly
installed for each dedicated line?
(Required)
Have the Residual Current Circuit Breaker (also known as Ground Fault
Circuit Interrupter) (2 poles, 30 mA residual, at least 20A capacity) been
correctly installed if required or recommended?
(Required)
Is the Power Distribution Unit (PDU) correctly installed?
(Required)
Are the grounding conductors properly installed for each wall receptacle
(wall socket)?
(Required)
Are the wall receptacles (wall sockets) suitable for the power cord plug type
provided by HP?
(Required)
Are the wall receptacles (wall sockets) and electrical installation suitable for
the printer's rated current ?
NOTE:
See
Wall receptacles and power cords
on page
10
and
Single-phase
power
on page
8
for further information.
(Required)
Are the wall receptacles (wall sockets) placed close enough to the printer
that the plugs can be plugged and unplugged easily?
(Required)
Site preparation checklist
15