Assembling the Rails, edge of the front rail. Run the front end of the power cord behind
View all EMC DS-16B manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 14 highlights
Installing the DS-16B2 Rails Assembling the Rails If this is a new installation in an EMC CLARiiON rack, the rails are pre-assembled. Follow these rail assembly instructions only if you are installing the switch in a non-EMC rack/cabinet. 1. Place the front rail down on a table. 2. Lay the ac power cord just below the lip that runs along the top edge of the front rail. Run the front end of the power cord behind the front flange. Be sure to leave a little extra length (6 to 8 inches) at the front end of the power cord. The length can be adjusted once the switch is installed on the rails. See Figure 10. Ac Power Cord Lip Rack Front/ Plug into Switch Front Rail Figure 10 Installing the ac Power Cord in the Front Rail Rack Rear/ Plug into PDU EMC2068 14 EMC Departmental Switch DS-16B2 Installation Guide