Dell S3048-ON Networking S3048–ON Getting Started Guide - Page 11
Install the S3048-ON System, Installing a 1U Front-Rack
![]() |
View all Dell S3048-ON manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 11 highlights
Figure 4. Four-Post Threaded Configuration Install the S3048-ON System You can mount the system in the 1U front-rack or 1U two-post (flush and center) configurations. The following is an example of a front-rack configuration. For the 1U two-post (flush and center) configurations, slide the system into the rails in the same manner as the four-post configurations. Installing a 1U Front-Rack You must configure the rails that are attached to the system. 1 Attach the switch rails (inner chassis members) to the S3048-ON system. Item 3 in the following illustration shows the detail for the front standoff with the locking tab. Install the Hardware 11
![](/manual_guide/products/dell-s3048on-networking-s3048x2013on-getting-started-guide-cba1c6d/11.png)
Figure 4. Four-Post Threaded Configuration
Install the S3048-ON System
You can mount the system in the 1U front-rack or 1U two-post (flush and center)
configurations. The following is an example of a front-rack configuration.
For the 1U two-post (flush and center) configurations, slide the system into the rails
in the same manner as the four-post configurations.
Installing a 1U Front-Rack
You must configure the rails that are attached to the system.
1
Attach the switch rails (inner chassis members) to the S3048–ON system. Item
3 in the following illustration shows the detail for the front standoff with the
locking tab.
Install the Hardware
11