Cisco ACI validation, 9.2.1 Verify vPC configuration

Page 26 highlights

9.2 Cisco ACI validation 9.2.1 Verify vPC configuration Verify the vPC connection from the Cisco ACI fabric to the S5248F-ON VLT, shown in Figure 6, is up and properly configured to enable designated VLANs and EPGs. This is done as follows: 1. In the APIC GUI, go to Fabric > Inventory > Pod name > Leaf name > Interfaces > vPC Interfaces and navigate to the applicable port channel/vPC policy group as shown in Figure 12. Cisco ACI vPC port channel and interfaces 2. Verify that the port channel uses active LACP and is operationally up 3. Verify all leaf switch interfaces in the vPC, for example, eth1/51-52, are listed beneath the port channel and are also up. 26 Dell EMC Networking OS10 Enterprise Edition Deployment Guide with Cisco ACI

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34

26
Dell EMC Networking OS10 Enterprise Edition Deployment Guide with Cisco ACI
9.2
Cisco ACI validation
9.2.1
Verify vPC configuration
Verify the vPC connection from the Cisco ACI fabric to the S5248F-ON VLT, shown in Figure 6, is up and
properly configured to enable designated VLANs and EPGs. This is done as follows:
1.
In the APIC GUI, go to
Fabric > Inventory >
Pod name
>
Leaf name
> Interfaces > vPC Interfaces
and navigate to the applicable port channel/vPC policy group as shown in Figure 12.
Cisco ACI vPC port channel and interfaces
2.
Verify that the port channel uses active LACP and is operationally up
3.
Verify all leaf switch interfaces in the vPC, for example, eth1/51-52, are listed beneath the port
channel and are also up.