Xerox 6180N DocuSP 61xx version 3.6 - Installation Planning Guide - Page 17

Getting Ready, for the DocuSP Installation - installation guide

Page 17 highlights

Planning for the installation Before scheduling delivery of the DocuTech system The following activities should be completed before you schedule a delivery date for the DocuTech system: • Select a location for the DocuTech system. • Prepare the site: - Install any required electrical service. Order Xerox receptacle kits if required. Refer to the section, "Electrical requirements", in chapter 3 for further information. - Install any required Ethernet hardware. - Complete the heat management worksheets included in the section, "Heat management", in chapter 3. Perform any modifications to the air handling capabilities of the installation site based on the results of your assessment. - Reserve a network address and hostname for each DocuSP controller workstation. • Identify networked client workstations that will submit jobs. Ensure that the hardware, operating system, and network protocols are supported by the DocuSP controller. • Complete the Installation Worksheets from the Getting Ready for the DocuSP Installation guide. After the preceding activities are complete, schedule a delivery date for the DocuTech hardware. This should be done with your Xerox sales representative. After scheduling delivery The following activities should begin at least two weeks prior to the scheduled delivery date of the DocuTech system to your location: • Perform a final inspection of the installation site. • Order the required consumable supplies that will be used during the installation process. The minimum supplies required during installation are: - Paper, 2 cartons - Developer, 1 carton - Fuser agent, 2 cartons - Binder tape and stitcher wire DocuTech 61xx Installation Planning Guide 3-3

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • 51
  • 52
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60

Planning for the installation
DocuTech 61xx Installation Planning Guide
3-3
Before scheduling delivery of the DocuTech system
The following activities should be completed before you
schedule a delivery date for the DocuTech system:
Select a location for the DocuTech system.
Prepare the site:
Install any required electrical service. Order Xerox
receptacle kits if required. Refer to the section, “Electrical
requirements”, in chapter 3 for further information.
Install any required Ethernet hardware.
Complete the heat management worksheets included in
the section, “Heat management”, in chapter 3. Perform
any modifications to the air handling capabilities of the
installation site based on the results of your assessment.
Reserve a network address and hostname for each
DocuSP controller workstation.
Identify networked client workstations that will submit jobs.
Ensure that the hardware, operating system, and network
protocols are supported by the DocuSP controller.
Complete the Installation Worksheets from the
Getting Ready
for the DocuSP Installation
guide.
After the preceding activities are complete, schedule a delivery
date for the DocuTech hardware. This should be done with your
Xerox sales representative.
After scheduling delivery
The following activities should begin at least two weeks prior to
the scheduled delivery date of the DocuTech system to your
location:
Perform a final inspection of the installation site.
Order the required consumable supplies that will be used
during the installation process. The minimum supplies
required during installation are:
Paper, 2 cartons
Developer, 1 carton
Fuser agent, 2 cartons
Binder tape and stitcher wire