Dell Force10 S25N-S50N Installing S25N and S25V Systems - Page 25
Installing S25N and S25V Systems, Four-Post Rack-mounting with Cage Nuts
View all Dell Force10 S25N-S50N manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 25 highlights
Step 4 Task Position the cage nuts over the holes on each bracket flange and each rack post. Figure 10 Four-Post Rack-mounting with Cage Nuts AC STACK ID XFP25 XFP26 Alarm DC 27 P28 S50-01-GE-24V fn00147d_s25N 5 Align the rack filler panel to the rear bracket and rack posts. Secure by inserting two screws into the hole in the filler panel through to the holes in the rack post. Figure 11 Four-Post Rack-mounting with Cage Nuts AC STACK ID XFP25 XFP26 Alarm DC 27 P28 S50-01-GE-24V Installing S25N and S25V Systems fn00147e_s25N 25
Installing S25N and S25V Systems
25
4
Position the cage nuts over the holes on each bracket flange and each rack post.
Figure 10
Four-Post Rack-mounting with Cage Nuts
5
Align the rack filler panel to the rear bracket and rack posts. Secure by inserting two screws into the hole in the
filler panel through to the holes in the rack post.
Figure 11
Four-Post Rack-mounting with Cage Nuts
Step
Task
fn00147d_s25N
fn00147e_s25N