Cable the Top-of-Rack switches to the core uplinks Cable the Top-of-Rack (ToR) switches to the core uplinks. Core uplinks Uplink A Uplink B 1 3 4 2 Figure 20. ToR switch connections to the core uplinks Table 22. Steps to connect to the ToR switches to the core uplinks 1 Connect port 30 of the bottom ToR switch to the core Uplink A. 2 Connect port 29 of the bottom ToR switch to the core Uplink B. 3 Connect port 29 of the top ToR switch to the core Uplink A. 4 Connect port 30 of the top ToR switch to the core Uplink B. NOTE: Work with your network administrator to determine the uplink ports to which the ToR switches will connect. 60 PowerStore X model: Cabling the appliance to the switches
Cable the Top-of-Rack switches to the core uplinks
Cable the Top-of-Rack (ToR) switches to the core uplinks.
Uplink A
Uplink B
Core uplinks
3
4
1
2
Figure 20. ToR switch connections to the core uplinks
Table 22. Steps to connect to the ToR switches to the core uplinks
1
Connect port 30 of the bottom ToR switch to the core Uplink A.
2
Connect port 29 of the bottom ToR switch to the core Uplink B.
3
Connect port 29 of the top ToR switch to the core Uplink A.
4
Connect port 30 of the top ToR switch to the core Uplink B.
NOTE:
Work with your network administrator to determine the uplink ports to which the ToR switches will connect.