Step 18. Connect the Power Cables to Electrical Outlets, Step 19. Your System Hardware is Now Set Up - service mode
View all IBM 9114-275 manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 30 highlights
Step 18. Connect the Power Cables to Electrical Outlets Connect the power source to the system unit. After 10 to 20 seconds, the system comes up to standby mode. The indicators of standby mode are as follows: v The power LED is slowly blinking. v OK is visible in the operator panel display. The following illustration shows the operator panel in standby mode with OK visible in the operator panel display. 1 Operator Panel Display 2 Attention LED 3 System Reset Button 4 Power LED 5 Power-On Button 6 Power-On Button Guard 7 Service Processor Reset Switch (Pinhole) 8 Serial Number Label If your system does not come up to standby mode, check all cables for good connection. If you cannot find a problem, call your support center for assistance. Step 19. Your System Hardware is Now Set Up Arrange your system unit and attached devices so that you can use them comfortably. If an operating system has been preinstalled in your system, continue to "Step 20. Start Your Model 275" on page 15. If you plan to install the operating system now, see the installation instructions provided with your operating system. Installation of the operating system can be accomplished in one of the following ways: v Installed from a CD (if a CD-ROM drive is installed). On the IntelliStation POWER 9114 Model 275, the CD-ROM drive is a customer-installable option. v If you are installing the AIX operating system, AIX can be installed from a Network Installation Management (NIM) server. For information about installing AIX from a NIM server, see the AIX 5L Installation Guide and Reference, order number SC23-4389. For other software installation, refer to the documentation provided with the software. 14 IntelliStation POWER 9114 Model 275 Installation Guide