HP bc1000 Setup & Installation Guide - Page 37
Engage the locking gear, Once the right rack rail is properly installed, install the left rack rail
View all HP bc1000 manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 37 highlights
Installing and Cabling the HP CCI Solution 6. Compress the spring-loaded rack rail toward the rear of the rack 1. 7. Using the marks you made when measuring with the template, align the front of the right rail with the holes and release the rail, allowing it to lock into position 2. 8. Engage the locking gear 3. Inserting the front of the rack rail and engaging the locking gear Ä CAUTION: Rack rails must be installed as tightly as possible. Failure to obtain a correct fit may result in damage to equipment. Once the right rack rail is properly installed, install the left rack rail using the same procedure. Setup and Installation Guide www.hp.com 4-9
Setup and Installation Guide
www.hp.com
4-9
Installing and Cabling the HP CCI Solution
6. Compress the spring-loaded rack rail toward the rear of the
rack
1
.
7. Using the marks you made when measuring with the template,
align the front of the right rail with the holes and release the rail,
allowing it to lock into position
2
.
8. Engage the locking gear
3
.
Inserting the front of the rack rail and engaging the locking gear
Ä
CAUTION:
Rack rails must be installed as tightly as possible. Failure to
obtain a correct fit may result in damage to equipment.
Once the right rack rail is properly installed, install the left rack rail
using the same procedure.