HP Surestore 64 FW 05.01.00 and SW 07.01.00 Director 2/64 Installation Guide ( - Page 50

/10000/11000 Rack Installation, Install the Shelf Brackets in a 9000/10000/11000 Rack

Page 50 highlights

Installing and Configuring the Director 2/64 WARNING: The Director 2/64 weighs approximately 115 pounds. Use proper handling and lifting equipment to reduce the possibility of injury or product damage. Two people will need to work together to transfer the director to the lift. Make sure the wheels of the lift cannot roll as you transfer the director to the lift. Move the director slowly and carefully onto the lift to prevent back and hand injury. Dropping the director could injure personnel or damage the equipment. 1. Position the lift device next to the director. 2. Using a pallet jack, raise the pallet on which the director is mounted to the same height as the top surface of the lift device. 3. Slide the director across from the pallet to the lift device. 4. Determine the appropriate rack mount position. Remember that the director is 9U (15.75 inches) high. 9000/10000/11000 Rack Installation To install the director in a HP 9000/10000/11000 rack, complete the procedures in the following sections: ■ Install the Shelf Brackets in a 9000/10000/11000 Rack, page 50 ■ Prepare the Switch for Installation, page 51 ■ Finalize the Rack Mounting Procedure, page 54 Install the Shelf Brackets in a 9000/10000/11000 Rack Use these steps to install the two shelf brackets in the rack. Note: Consider leaving the bottom and top U positions open to permit easy accessibility to the cables entering and exiting the rack. 1. Determine the appropriate placement for the switch inside the rack. It is important to consider the number of switches you intend to install. See "Tips for Installing More than One Switch" on page 49. 2. Locate the small, round marker hole on the rails that coincides with the location selected in step 1. Each marker hole delineates the beginning of one rail unit, or U. 50 Director 2/64 Installation Guide

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • 51
  • 52
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • 69
  • 70
  • 71
  • 72
  • 73
  • 74
  • 75
  • 76
  • 77
  • 78
  • 79
  • 80
  • 81
  • 82
  • 83
  • 84
  • 85
  • 86
  • 87
  • 88
  • 89
  • 90
  • 91
  • 92
  • 93
  • 94
  • 95
  • 96
  • 97
  • 98
  • 99
  • 100
  • 101
  • 102
  • 103
  • 104
  • 105
  • 106
  • 107
  • 108
  • 109
  • 110
  • 111
  • 112
  • 113
  • 114
  • 115
  • 116
  • 117
  • 118
  • 119
  • 120
  • 121
  • 122
  • 123
  • 124
  • 125
  • 126
  • 127
  • 128
  • 129
  • 130
  • 131
  • 132
  • 133
  • 134
  • 135
  • 136
  • 137
  • 138
  • 139
  • 140
  • 141
  • 142
  • 143
  • 144
  • 145
  • 146
  • 147
  • 148

Installing and Configuring the Director 2/64
50
Director 2/64 Installation Guide
WARNING:
The Director 2/64 weighs approximately 115 pounds. Use
proper handling and lifting equipment to reduce the possibility of injury or
product damage.
Two people will need to work together to transfer the director to the lift. Make
sure the wheels of the lift cannot roll as you transfer the director to the lift.
Move the director slowly and carefully onto the lift to prevent back and hand
injury. Dropping the director could injure personnel or damage the equipment.
1.
Position the lift device next to the director.
2.
Using a pallet jack, raise the pallet on which the director is mounted to the
same height as the top surface of the lift device.
3.
Slide the director across from the pallet to the lift device.
4.
Determine the appropriate rack mount position. Remember that the director is
9U (15.75 inches) high.
9000/10000/11000 Rack Installation
To install the director in a HP 9000/10000/11000 rack, complete the procedures in
the following sections:
Install the Shelf Brackets in a 9000/10000/11000 Rack
, page 50
Prepare the Switch for Installation
, page 51
Finalize the Rack Mounting Procedure
, page 54
Install the Shelf Brackets in a 9000/10000/11000 Rack
Use these steps to install the two shelf brackets in the rack.
Note:
Consider leaving the bottom and top U positions open to permit easy
accessibility to the cables entering and exiting the rack.
1.
Determine the appropriate placement for the switch inside the rack. It is
important to consider the number of switches you intend to install. See “
Tips
for Installing More than One Switch
” on page 49.
2.
Locate the small, round marker hole on the rails that coincides with the
location selected in
step 1
. Each marker hole delineates the beginning of one
rail unit, or U.